How to configure 2 GRIDs and run Copy Audit report with Vantage
search cancel

How to configure 2 GRIDs and run Copy Audit report with Vantage

book

Article ID: 111721

calendar_today

Updated On:

Products

Vantage Storage Resource Manager

Issue/Introduction

How to configure 2 GRIDs and get the Copy Audit report?

Environment

Release: SMV3EN00200-14.0-Graphical Management Interface
Component:

Resolution

How to configure one GRID is mentioned in the documentation, however for two GRIDs the only way is as follow:

1) Change VTSAUDIT (INCLUDE 18005,17988)   => GRID3

2) F VANTAGE,REFRESH,VKGPARMS

3) Start "copy audit report"

4) Change VTSAUDIT (INCLUDE 17992,17990) => GRID4

5) F VANTAGE,REFRESH,VKGPARMS

6) Start "copy audit report"
 

Additional Information

Here is the documentation link for one Grid: 
https://docops.ca.com/ca-vantage-storage-resource-manager/14-0/en/configuring/configuring-the-tape-resource-option/configure-virtual-tape-systems
https://docops.ca.com/ca-vantage-storage-resource-manager/14-0/en/configuring/system-parameters/vkgparms-parameter-descriptions-s-to-z-inclusive