User Name Appears as Last updated for Tasks which the user never updated it

book

Article ID: 111065

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

One of the users has made updates only to the risks, issues and phase attributes and made no updates to the Tasks. However in the system it shows his name as updated for Tasks. Not sure why does this happen?

Environment

Release:
Component: ODPRM

Resolution

DE43325 - Why does a simple save at project level update Task last updated fields?
Fixed in 15.5.1