CA PPM: Allocation Discrepency portlet Time Scale

book

Article ID: 111023

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS - Application Clarity PPM On Premise

Issue/Introduction



Why doesn't the Allocation Discrepancy portlet show  the same hours as the Weekly Detail, when filtered by the same  Time Scale?

Environment

Release: CODFSS99000-15.3-PPM SAAS FedRAMP-Sandbox-Small Environment
Component:

Resolution

The Allocation Discrepancy portlet uses the last Time Scale period when displaying data.
The weekly detail portlet uses the periods you select in the TSV.

An example is:

We are in week of 8/13
Weekly Detail Allocation 
Prior week (8/6) = 22
Current week (8/13) = 40

Allocation Discrepancy Portlet set for 1 Period and Weekly Time Scale shows
Allocation = 22 (week of 8/6)