In the MSP New Driver, ETC Hours Shift Away from Whole Numbers
book
Article ID: 110240
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
ETC hours are shifting away from whole numbers and are rounded off over time. This occurs when working on a project in PPM 15.2 and using the new XML driver.
Steps to Reproduce: 1. Create a project with dates: 7/30/2018 - 6/24/2020 2. Staff a resource to the team 3. Create a fixed duration task with dates the same as the project 4. Assign a resource to the task with a uniform loading pattern and 100 hours of ETC 5. Without making any additional changes, export the project to MSP and save it back to PPM a few times
Expected Results: The ETC always remains at 100 hours in both MSP and PPM Actual Results: The ETC starts out as 100 hours, but eventually starts rounding off to numbers, such as 99.98 or 99.95