Issue/Introduction

When viewing a project in Gantt view, I am unable to link.  I can see the link icon because the chart, however it is grayed out and unable to click it.

Environment

All supported PPM environments

Cause

There were changes made to the project causing it to be in edit mode.  If it is in edit mode, you will not be able to link.

Resolution

Save project.  The link icon will become visible and you will be able to link.