Issue/Introduction
When viewing a project in Gantt view, I am unable to link. I can see the link icon because the chart, however it is grayed out and unable to click it.
Environment
All supported PPM environments
Cause
There were changes made to the project causing it to be in edit mode. If it is in edit mode, you will not be able to link.
Resolution
Save project. The link icon will become visible and you will be able to link.