Baseline Usage attribute of Project object is not available for ad hoc view
book
Article ID: 109778
calendar_today
Updated On:
Products
CLARITY PPM FOR ITGCLARITY PPM FEDERALClarity PPM SaaSClarity PPM On Premise
Issue/Introduction
We need to add Baseline Usage field to an ad hoc view, but even though it' s listed as an attribute of the Project object, it is not available on the list of fields that are available for ad hoc views of the Project Management domain. How to make this field available for the view?
Environment
Release: Component: ODJSP
Resolution
Currently the 'Baseline Usage' attribute on Project Object is not Data warehouse enabled by default. In the Project domain of within Advanced Reporting, if you drill down as follows then you can get Total Baseline Hours.
Project => Summary Totals =>Project => Total Hours => Total Baseline Hours or Project => Summary Totals => Task => Task Hours => Task Total Baseline Hours or Project => Summary Totals => Assignment => Assignment Total Baseline Hours