How to add the past ETC data?
search cancel

How to add the past ETC data?

book

Article ID: 109651

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction



We add the past ETC in a Task allocation screen and save it. However it is disappeared. Why? We would like to add past ETC in a Task allocation screen. Is there a way to add it?

Environment

Release:
Component: ODFNM

Resolution

The ETC is calculated automatically by using Actual. As a result, if Actual is added already, a Timesheet is posted. the past ETC cannot be added, and which is working by design. In order to add the past ETC, you need to create a new Task. If no actual is added to an existing task, you will be able to add a new ETC to the past week.