Key Milestones Sort Order on Reports
search cancel

Key Milestones Sort Order on Reports

book

Article ID: 108091

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction



On the Key Milestones section of the Project Status Detail report, why are the milestones not listed in ascending order by the finish date?

Environment

Release:
Component: ODJSP

Resolution

The query in the out of the box Project Status Detail report does not include an 'order by' to sort the results by any particular column. By default, the task milestone's internal PRID is what is used for the sort. The task PRID is generated by the system when the milestone is created, so typically the order will be the same as the order in which the milestones were created.