Issue/Introduction

The filter "First Day of Work Week" in the "Resource Time review by Manager" (Reports & Jobs) report doesn't show any values. The values are shown in the lookup RSM_RTP_TRANSLATIONS and are active.

Environment

Release: All Supported
Component: Clarity Jaspersoft

Resolution

Run the Load Data Warehouse (DWH) Job in Full mode that will populate the dwh_lkp_translation table.