Issue/Introduction



Why for some baselines we are not able to see 'baseline start' and 'baseline finish' in tasks (ex tasks properties or gantt view)
 

Environment

All CA PPM Versions

Resolution

The main reason could be because the baseline was created before the tasks creation, since the tasks don't exist at the moment of baseline creation does not have reference corresponding that baseline.