PPM Resource Actuals Calculation
book
Article ID: 107038
calendar_today
Updated On:
Products
Clarity PPM SaaS
Clarity PPM On Premise
Issue/Introduction
Actuals for expense resources are showing an unexpected value on their task assignments.
How are the Actuals from financial transactions being calculated for different types of resources?
Resolution
- For a Non-Expense resource (Labor/Material/Equipment), the Actuals is Quantity.
- For an Expense resource, the Actuals is Amount (Quantity * Rate). For expense resources the recommendation is to use 1 for the Rate.