CA PPM New UX Timesheet shows "Other Work" as a 5XXXXXX and does not reflect the name in Classic PPM
book
Article ID: 106379
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
When I add "Other Work" to my Timesheet via the New UX the "Work Name/ID" shows as a 5XXXXXX number and not the "Other Work" name in Classic PPM.
Steps To Reproduce: 1. Create a new Timesheet in the New UX 2. Choose Type: Other Work 3. Click the Add and Close button Expected Results: In the "Other Work" section of the timesheet the name should appear as it appears in Classic PPM. Actual Results: The "Other Work" name appears as a 5XXXXXX number.
Environment
CA PPM 15.3 and higher
Cause
This is due to the task name in the XOG Object: inv_others_write.xml.
Resolution
I renamed the "Other Work" task name in XOG Object: inv_others_write.xml to reflect the "Other Work" name ID in Classic PPM.