The Project Schedule report shows a red indicator (late) at the project level. 
The project is completed, and the Finish Date has already passed. 
How to change this indicator to green (the project is on track)?    

Environment

Release:
Component: ODPRM

Resolution

The following must be done: 
1. Complete all the Tasks in the project (Status:Completed, %Complete:100). 
2. Complete the Project (Progress: Completed). 
3. Run the Update Report Tables job. 
4. Run the Load Data Warehouse job. 

Additional Information

What is the difference between the Status indicator on the Schedule and Performance page of the project and the Schedule Status on the Status report?
> https://comm.support.ca.com/kb/what-is-the-difference-between-the-status-indicator-on-the-schedule-and-performance-page-of-the-project-and-the-schedule-status-on-the-status-report/kb000097796

Tasks that are scheduled to finish in the future are being marked as late
>https://comm.support.ca.com/kb/tasks-that-are-scheduled-to-finish-in-the-future-are-being-marked-as-late/kb000097136