Which OOTB CA PPM Jaspersoft Report can we use to compare the weekly forecast to actual hours in a project?
search cancel

Which OOTB CA PPM Jaspersoft Report can we use to compare the weekly forecast to actual hours in a project?

book

Article ID: 106345

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction



How do we analyze historical weekly forecast to actual hours in a project? Which Jaspersoft Out of the Box (OOTB) report can we use to view this analysis back to the project's inception?

Environment

Release:
Component: ODRSM

Resolution

The OOTB report that most closely matches this requirement is the "Resource Allocations and Assignments" report. You can review a summary of this report here

The only caveat is that the Assignment values that it shows are total usage (ETC + Actuals). Theoretically, periods in the past should only have Actuals and periods in the future should only have ETC's. We do not have any OOTB reports that splits these metrics up.