New UX Timesheets Display Copy Hours Option Even When Days Are Selected As Work Unit

book

Article ID: 106278

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

New UX Timesheets display Copy Hours option even when Days are selected as Work Unit 

Steps to Reproduce
  1. In the Classic UX, configure PPM to use Days instead of Hours as default work unit: 
    • Administration > Project Management > Timesheet Options > Display Units > Days 
    • Administration > Project Management > Settings > Default Display Unit for Work Effort > Days 
  2. Open the New UX > Timesheets view 
  3. Choose any period that does not have any Timesheet created 
  4. Observe the "Copy previous timesheet" option 
Expected Results: Option is "Copy days" or "Copy effort" 
Actual Results: Option is "Copy hours"

Cause

This issue has been reported to Engineering as DE42301 for review.

Environment

This issue has been reported for PPM 15.3.

Resolution

This issue has been reviewed by Engineering and the fix (option shown is "Copy effort") is targeted to be included in PPM 15.6.