After Refreshing PPM Data From Prod to Test All Projects are being set to sync with CA Agile Central
book
Article ID: 103685
calendar_today
Updated On:
Products
CLARITY PPM FOR ITGCLARITY PPM FEDERALClarity PPM SaaS - ApplicationClarity PPM On Premise
Issue/Introduction
After refreshing the data from PROD to TEST, we manually unchecked the box on all projects to sync with CA Agile Central, however we are finding that overnight, they are all reset to sync again automatically.
Cause
This was caused by a custom job that was put in place which was automatically setting all projects to sync with CA Agile Central. The job was running on a schedule every night.
Environment
Release: Component: ODRLY
Resolution
Disabling the custom job prevented the projects from being rest to sync with CA Agile Central.