PPM: About Role Capacity and Demand portlet in portfolio

book

Article ID: 103493

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS - Application Clarity PPM On Premise

Issue/Introduction



About "Role Capacity and Demand" portlet on Capacity tab in Portfolio.
Some role is not calculated correctly. 
How does "Role Capacity and Demand" portlet calculate total Allocation for each Roles?

Environment

Release:


Component:

Resolution

The "Role Capacity and Demand" portlet is provided by PMO Accelerator and it uses Project Role for culculation.
It sums up allocations for each Project Role.
If resource has primary role, the same role will be set as Project Role when resource is added to team staff.
If Project Role of resource is blank, "Role Capacity and Demand" portlet will not calculate total allocation for that resources.