Job is running before its predecessors complete
search cancel

Job is running before its predecessors complete

book

Article ID: 103102

calendar_today

Updated On:

Products

Jobtrac

Issue/Introduction



How to determine if an event is correctly set up so that it does not run before its predecessor completes?

Environment

Release:
Component: JOBTRC

Resolution

Any job that is set up with predecessors should wait until the predecessor events successfully complete  their execution
before that event can be submitted.  If an event runs before its predecessors, it may be that the SCL is set up incorrectly
and no actual predecessor events were defined.  Select the event in question from the checkpoint  by placing an 'S' by  
it and verify whether the Schedule Event Detail shows any predecessor events are define.   To add the appropriate
predecessors, update the SCL to include the desired predecessors in the Successor/Predecessor field.

As always, please contact CA Technologies Support for CA Jobtrac Job Management if you have further questions.