Issue/Introduction

When updating the calendar the allocation is changing the allocation and availability for the month.

Resolution

  • This is working as designed and as documented. 
  • When a calendar entry is changed for a resource, the allocations and availability will change as well. 
  • For example, if you mark a day on a resource's calendar as "non-working" - then the hours for that day should be subtracted from the allocation/availability for that resource in the team detail view.