Clarity: Why do allocations and availability change when updating the calendar for a resource?
book
Article ID: 102782
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
When updating the calendar the allocation is changing the allocation and availability for the month.
Resolution
This is working as designed and as documented.
When a calendar entry is changed for a resource, the allocations and availability will change as well.
For example, if you mark a day on a resource's calendar as "non-working" - then the hours for that day should be subtracted from the allocation/availability for that resource in the team detail view.