"Could not create taskboard" error due to Access Right issue
book
Article ID: 102443
calendar_today
Updated On:
Products
Clarity PPM On Premise
Issue/Introduction
- As a team member in the new Clarity User Experience (UX/UI), NOT the Classic, we are unable to create task.
- We get a message error on top like "Could not create taskboard"
Cause
Team resource needs to add permissions
Environment
Release: All Supported Releases
Component: Clarity Administration
Resolution
Add one of these two permissions:
- Project - Edit Management - All
- Project - Task Management