Issue/Introduction
The ETC for labour resources in the staff list differs from the ETC amount populated in the Task list.
Cause
The "Work Effort Unit of Measure" is set to 'FTE'
Environment
Release:
Component: PPMPRD
Resolution
-Select the Configure Icon -Select the Field configuration tab -Change the "Work Effort Unit of Measure" from FTE to Hours