ETC In Staff List vs Task List

book

Article ID: 102077

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

The ETC for labour resources in the staff list differs from the ETC amount populated in the Task list. 

Cause

The "Work Effort Unit of Measure" is set to 'FTE'

Environment

Release:
Component: PPMPRD

Resolution

-Select the Configure Icon -Select the Field configuration tab -Change the "Work Effort Unit of Measure" from FTE to Hours