Which data shows start date, finish date, Progress Through Date Attribute and Progress Percent Attribute on mouse over of Gantt ?

book

Article ID: 101651

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS - Application Clarity PPM On Premise

Issue/Introduction



Which data shows start date, finish date, Progress Through Date Attribute and Progress Percent Attribute on mouse over of Gantt ? 

<Please see attached file for image>

User-added image

Environment

Release: CODFSS99000-15.3-PPM SAAS FedRAMP-Sandbox-Small Environment
Component:

Resolution

You can see the default setting value on Gantt Chart Column Settings as follows.

<Please see attached file for image>

User-added image

You can see %Expended on schedule and performance content and the value is calculated by Actuals / EAC(Total Labor Effort). 

<Please see attached file for image>

User-added image

Attachments

1558700878588000101651_sktwi1f5rjvs16kaw.jpeg get_app
1558700876971000101651_sktwi1f5rjvs16kav.jpeg get_app
1558700874945000101651_sktwi1f5rjvs16kau.jpeg get_app